Book 10 · Maintenance plan

One route round the plant. Every check, every grease point.

The checklists bring the check tables of all the books together, so the plant team walks the plant in a fixed order instead of opening thirteen books. Tick them on a phone, or print them and post them in the control cabin.

Daily walk-round

OPERATOR · before the first batch, in the order of material flow

0 / 16 done
#AreaCheckStop if…Book
1 Whole plant Guards in place; walkways clear; nobody inside equipment Guard missing 1 · 5 · 8
2 Control cabin Alarms read; supply voltage normal; PC and air conditioning working Phase missing 8
3 Compressor Running; oil level; no alarm; condensate drained Alarm, oil low 7
4 Air system Main pressure normal; dryer in the green; FRL bowls dry Pressure below minimum 7
5 Water Tank level; pump normal; booster not short-cycling No water 6
6 Aggregate bins Levels; no mixing between bins; grids in place; gates close fully Gate not closing; grid missing 4
7 Conveyors Pull-cords; start warning; belt centred; no spillage at the tail; cleaners working Pull-cord broken; belt rubbing the frame 5
8 Skip (if fitted) Area under the track clear; stops at its marks; brake holds; rope looks normal Creep; overrun; damaged rope 9
9 Silos Levels; filter air on; no dust at the safety valve; screws running quietly Powder at the safety valve (investigate) 2
10 Scales Zero all scales; no material stuck; nothing touching the hoppers Zero will not hold 3
11 Admixture Tank levels; no leaks; agitation running 3 · 11
12 Mixer Clean; lids and interlocks closed; grease reservoir level; grease at shaft ends; door opens, closes and signals Interlock fault; no grease at the seals 1
13 Hydraulic pack Oil level; no new leaks Hose leaking 6
14 Loading points Ground hopper grids intact; wheel stops in place; fill pipes capped and locked; truck bay clear and lit Grid damaged 12
15 E-stops Not damaged; reset normally 8
16 First batch Watch the full cycle; listen for new noises Any abnormal noise or overload —

Date ______________   Signed ______________

Weekly

TECHNICIAN · locked out where hands go near moving parts

0 / 13 done
#AreaCheckStop if…Book
1 Mixer Paddle-to-liner gap (3–5 mm); arm and paddle bolts; liner wear; door seal; wash heads clear; weekly grease points 1
2 Silo filters Cartridges, pulse valves, filter air pressure 2
3 Screws Noise, motor current, seals at inlet and outlet; grease 2
4 Scales Reference-weight check; cleaning 3
5 Bins Gate seals, cylinders, position sensors; vibrator mountings 4
6 Conveyors Cleaner blades and tension; V-plough; skirts; idlers turning; take-up position 5
7 Water Strainers clean; booster cut-in and cut-out 6
8 Hydraulics Hoses (with cardboard, never hands); cylinder rods; filter indicator 6
9 Air Line filter drains; cylinder rods; silencers; sensors tight 7
10 Electrical Sensors tight and clean; motor fins clean; junction boxes closed 8
11 Skip Wheels, rails, switch mountings, rope terminations, sheaves 9
12 Recycling and dust Reclaimer screw flights and tail bearing; screen mesh; dust collector pulse valves and discharge 11
13 Whole plant Spillage removed under conveyors and around bins; housekeeping —

Date ______________   Signed ______________

Monthly

TECHNICIAN · ELECTRICIAN where needed

0 / 11 done
#AreaCheckStop if…Book
1 Safety functions Test every E-stop, pull-cord (both directions), mixer lid interlock, sway switch, skip over-run and slack-rope switch; record the results 5 · 8 · 9
2 Mixer Gearbox oil level; breather; V-belt tension; mounting bolts; door hydraulics or pneumatics 1
3 Silos Level sensors; safety valve free; pressure sensor test; butterfly valves 2
4 Scales Zero drift trend; junction boxes dry; load cell cables 3
5 Conveyors Splices; covers and edges; lagging; pulley bearing temperature; backstop; chevron profiles; gearbox oil 5
6 Pumps and hydraulics Bearing noise; motor current; wash nozzles; oil condition (milky, dark) 6
7 Air Leak walk with the plant quiet; test automatic drains; regulator settings 7
8 Electrical Main motor currents; voltage and unbalance; panel AC and fans; cables; PLC and batching data backup 8
9 Skip Full-length rope inspection and diameter; brake gap and holding test; drum spooling 9
10 Lubrication All monthly points of the chart; grease record reviewed for missed points 10
11 Structure Handrails, gratings, ladders; loose bolts; corrosion spots; vibrating supports 13

Date ______________   Signed ______________

Every 3 months

TECHNICIAN

0 / 7 done
#AreaCheckStop if…Book
1 Mixer Measure liner and paddle thickness; plan the wear-part order 1
2 Scales Partial verification at selected points 3
3 Moisture probes Calibration check 3 · 4
4 Conveyors Pulley alignment; frame; take-up travel remaining 5
5 HP wash pump and slurry pumps Oil change per maker; impeller and liner wear 6
6 Compressor Air filter inspection; dryer condenser cleaned 7
7 Mobile chassis (standing) Tyre pressure and condition; corrosion; cylinder rods protected 13

Date ______________   Signed ______________

Every 6 months

TECHNICIAN · ELECTRICIAN

0 / 5 done
#AreaCheckStop if…Book
1 Scales Full calibration with test weights; records and labels 3
2 Silos Screw flight thickness; filter cartridges by differential pressure 2
3 Booster tank and accumulators Pre-charge pressure 6
4 Electrical Re-torque MCC terminals (isolated); earthing; surge protection; UPS test 8
5 Skip Rail gauge and alignment; sheave grooves; structure 9

Date ______________   Signed ______________

Every year

TECHNICIAN · ELECTRICIAN · COMPETENT PERSON

0 / 8 done
#AreaCheckStop if…Book
1 Electrical Infrared scan of panels under load; insulation resistance of main motors; drive service 8
2 Hydraulics Oil and filter change (or 2,000 h); hose register review 6
3 Compressor and air Service per maker hours; receiver safety valve and legal inspection; line filter elements; drain service 7
4 Silos Safety valve springs and gaskets (about every 24 months); full silo protection service 2
5 Skip Thorough examination by a competent person (lifting equipment law) 9
6 Structure Full structural inspection: bolts, welds, corrosion, anchors, silo legs; plumb and level 13
7 Mobile chassis Bearings, brakes, suspension, lights — full running gear service 13
8 Documents and backups Wiring diagrams, lubrication chart, spare parts list updated; restore the PLC and batching backup on a spare PC 8 · 10

Date ______________   Signed ______________